Somasila Reservoir is made across stream Pennar close to Somasila, the village of Ananthasagaram Mandal in Nellore District of Andhra Pradesh.
The Project envisages storage of seventy eight.00TMC of water at F.R.L. +100.58M. The contemplated ayacut below the project is five, 84,500 acres in SPSR Nellore and Prakasam Districts. Out of that stabilization of wet ayacut below Pennar Delta Kanupur canal system and existing tanks in uplands is four,05,500acres and new I.D.is1, 79,000 acres. Out of the higher than ayacut, Associate in Nursing extent of eighty-two,500 acres stabilization and one,35,000 new I.D is below Somasila Project canals viz., GKNC Canal (North Feeder Channel ), south feeder channel and Kavali canal.The allocation of water for the higher than ayacut is sixty.892 TMC. It conjointly envisages to transmit thirty.00 TMCof water to Kandaleru Reservoir below Telugu Ganga Project for irrigating three, 00,000 Acres of I.D. ayacut in Nellore and Chittoor Districts besides fifteen.00 TMCof avatar water to Chennai town for water functions. additionally to the higher than two.40 TMC of water was allotted to Nellore, Kavali, Gudur and Tirupathi cities for water wants.
The Project envisages storage of seventy eight.00TMC of water at F.R.L. +100.58M. The contemplated ayacut below the project is five, 84,500 acres in SPSR Nellore and Prakasam Districts. Out of that stabilization of wet ayacut below Pennar Delta Kanupur canal system and existing tanks in uplands is four,05,500acres and new I.D.is1, 79,000 acres. Out of the higher than ayacut, Associate in Nursing extent of eighty-two,500 acres stabilization and one,35,000 new I.D is below Somasila Project canals viz., GKNC Canal (North Feeder Channel ), south feeder channel and Kavali canal.The allocation of water for the higher than ayacut is sixty.892 TMC. It conjointly envisages to transmit thirty.00 TMCof water to Kandaleru Reservoir below Telugu Ganga Project for irrigating three, 00,000 Acres of I.D. ayacut in Nellore and Chittoor Districts besides fifteen.00 TMCof avatar water to Chennai town for water functions. additionally to the higher than two.40 TMC of water was allotted to Nellore, Kavali, Gudur and Tirupathi cities for water wants.

The Andhra Pradesh State Electricity Board has sanctioned two x five M.W. mini HydelScheme for Power Generation at Somasila Dam, Nellore District for captive utilization in G.O. M.S.No.180, dated 29.12.1994 in favor of M/s.Balaji Power Corporation non-public restricted. and the govt. in G.O.Ms.No.100 I& CAD. TGP-I(2) Department, dated 9.7.1999 have issued no objection certificate at hand over the theme to the same firm for implementing the facility Project. consequently the firm has dead the mini Hydel Project together with civil, electrical and mechanical works and water is being equipped to powerhouse and project is commissioned within the year throughout Gregorian calendar month two005and it's increased to 2 X six MW i.e. 12 MW. Approval accorded for an extra capability of eleven MW and can get operation in due course. from this water is releasing to k r dam for the purpose of drinking water '
Salient Feature
Location of Headworks | : | |
Village | : | Somasila |
Mandal | : | Ananthasagaram |
District | : | Nellore (Foreshore area in Kadapa Dist.) |
River/Tributary | : | Pennar River |
Nearest City/ Town (including KMs.) | : | Nellore 90 KMs |
Name of the upper stream projects | : | Mylavaram Dam, Cheyyeru Project and Lower Sagileru.Project (Complete). |
Village benefited | : | 101 Nos |
Mandals benefited | : | 15 Nos |
Catchments area | : | 48,645 Sq.km |
Maximum Flood discharge (observed) | : | 6,26,274 Cusecs, 2001year |
Designed Discharge at F.R.L | : | 6,95,000 Cusecs |
Designed Discharge at M.W.L | : | 7,90,000 Cusecs |
Gross Capacity at FRL in TMC | : | 77.988 TMC |
Water spread area at FRL (Sq.Km.) | : | 212.285 Sq.km |
Water allocation | : | 60.892 TMC |
Average Monsoon rainfall | : | 1031.76 mm |
FRL/MWL | : | +100.58M/+101.80M |
Gross storage | : | 77.988 TMC. |
Dead Storage | : | 7.567 TMC |
Live storage between MDDL&FRL | : | 70.421 TMC |
The budget for the Year 2015-16 | : | Plan – 124.9800 Crs. |
Irrigation Potential: | : |
The total ayacut contemplated under the Project is .4,05,500 acres wet (stabilization) and 1, 79,000 acres (New I.D) ayacut.
Component Works | : | |
a) Earth Dam | : | |
i) Type of dam | : | Zoned Earth Dam |
ii)Total Length | : | 352 Meters |
iii)Top width | : | 18 Meters |
b) Non Over Flow Dam | : | |
i) Type of dam | : | Masonry Gravity |
ii) Total length | : | 172.53 Meters |
iii) Top level | : | 105.15Meters |
c) Spill Way | : | |
i) Type of Spill way | : | Ogee Type |
ii) Total Length | : | 236.21 Meters |
iii)Crest level | : | 86.87 Meters |
d) No.of Gates | : | 12 Nos. |
Size of the radial gates | : | 15.24 x 14.17 meters |
e)Maximum Designed Discharge | : | 6, 95,000 C/s at F.R.L.100.58 meters. 7, 90,000 C/s at M.W.L.101.80 meters |
Irrigation Potential:
The total ayacut contemplated under the Project is .4,05,500 acres wet (stabilization) and 1, 79,000 acres (New I.D) ayacut.
The Mandals covered are Alluru, Bogolu, Buchi, Dagadarthi, Indukurpet, Kovur, Kodavalur,Muthukur, Nellore, Sangam, Thotapalli Gudur, Venkatachalam, Vidavalur, Podalakur, Nellore Rural, Manubolu, Jaladanki, Kaligiri, Kavali, Kaluvoy, Chejerla, Podalakur, Ananthasagaram, Atmakur, Marripadu and A.S.Peta.